The
following transmission system additions, upgrades, and reconfigurations reflect
a preliminary list of forecasted projects from the KCPL 5yr. proposed Transmission
Services Construction Budget Plan for 2008-2012. These projects and/or dates
may be rescheduled or deleted and new projects may be added at any time.
2008
·
New
Pleasant Valley Substation
·
Upgrade
Stilwell – Bucyrus 161 kV Line
·
New Lackman Substation
·
New
Midtown – Crosstown 161 kV Line
·
Reconductor
·
Upgrade
·
New
Westside Substation
2009
·
Iatan
345 kV Substation Expansion and 345/161 Transformer
·
New Iatan 161 kV Substation
·
Reconductor
Craig – College 161 kV Line
·
New
Craig 161 kV Capacitor
·
Replace
2010
2011
·
New
Paola – Middle Creek –
·
New
Middle Creek Substation
2012
·
New
Hillsdale Substation
·
New
Cedar
·
New
Cedar
·
Upgrade
South Waverly 161/69kV transformer
·
Upgrade
Avondale –