The following Generation Interconnection Studies have been requested.

Study NumberDate RequestedPurpose of StudyRemarksReport
Gen-2004-003 2/4/2004  Request to interconnect 240 MW on the SWPS System Facililty Study Completed December 2005  Download 
Gen-2004-008 3/26/2004  Request to interconnect 900 MW on the KCPL System Facility Study completed December 2005  Download 
GEN-2004-010 4/7/2004  Request to interconnect 300 MW on the WERE system Facility Study completed September 2005  Download 
Gen-2004-014 4/22/2004  Request to interconnect 154.4 MW on the MIDW system Facility Study completed June 2007  Download 
Gen-2004-015 7/12/2005  Request to interconnect 170 MW on the SWPS System Facility Study completed October 2005  Download 
Gen-2004-016 7/15/2004  Request to interconnect 150 MW on the WERE system Facilities Study completed December 2005  Download 
GEN-2004-017 8/23/2004  Request to interconnect 250MW on the EDME system. Facility Study completed January 2006  Download 
GEN-2004-020 10/8/2005  Request to interconnect 27 MW on the AEPW System Feasibility Study completed October 2005  Download 
GEN-2004-023 10/26/2004  Request to interconnect 20.6 MW on the WFEC System Facility Study completed July 2005  Download 

Please send your requests to GIStudies@spp.org :

Manager, Generation Interconnections
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR 72223-4936