2005_Impact_Studies
The following Generation Interconnection Studies have been requested.

Study NumberDate RequestedPurpose of StudyRemarksReport
Gen-2005-002 1/18/2005  Request to interconnect 80 MW on the SWPS System Impact Study completed September '05  Download 
Gen-2005-003 1/21/2005  Request to interconnect 30.6 MW on the WFEC System Expedited Impact Study completed August 2005  Download 
Gen-2005-005 3/22/2005  Request to interconnect 18 MW on the OKGE System Impact Study completed November 2005  Download 
Gen-2005-006 3/22/2005  Request to interconnect 150 MW on the OKGE System. Impact Study completed November 2005  Download 
Gen-2005-007 3/23/2005  Request to interconnect 260 MW on the SWPS system Impact Study completed January 2006  Download 
Gen-2005-008 4/1/2005  Request to interconnect 130.5 MW on the OKGE system Impact Study completed January 2006  Download 
Gen-2005-010 7/28/2005  Request to interconnect 232.5 MW on the SWPS system Impact Study completed January 2006  Download 
GEN-2005-012 8/8/2005  Request to interconnect 400MW on the WEPL system Impact Study completed July 2006  Download 
Gen-2005-012 8/8/2005  Request to interconnect 400MW on the WEPL System Impact Study re-studied January 2007  Download 
Gen-2005-012 8/8/2005  Request to interconnect 400MW on the WEPL System Impact Re-Study completed November 2007  Download 
Gen-2005-012  8/8/2005  Request to interconnect 400MW on the WPEK system Impact Re-Study completed June 2008  Download 
GEN-2005-012 8/2/2005  Request to interconnect 248.4MW on the SUNC transmission system Posted Restudy 3/9/2011  Download 
GEN-2005-013 8/22/2005  Interconnect 201 MW on the Westar transmission system Impact Restudy posted 3/19/2010  Download 
GEN-2005-013 8/22/2005  Addendum to Impact Restudy Study completed May 2010  Download 
Gen-2005-013 8/22/2005  Request to interconnect 201 MW on the WERE system Impact Study Completed February 2006  Download 
Gen-2005-015 9/14/2005  Request to interconnect 150MW on the SWPS system Impact Study completed April 2006  Download 
Gen-2005-016 9/14/2005  Request to interconnecct 150MW on the WERE system Impact Study completed November 2006  Download 
Gen-2005-017 9/26/2005  Request to interconnect 340MW on the SWPS system Impact Study completed January 2007  Download 
Gen-2005-017  9/26/2005  Request to interconnect 340MW on the SWPS system Impact Re-Study completed November 2007  Download 
Gen-2005-021 10/24/2005  Request to interconnect 150MW on the SWPS system Impact Study completed September 2006  Download 
Gen-2005-022 12/13/2005  Request to interconnect 168MW on the AEP System Impact Study completed July 2006  Download 
Gen-2005-024 12/13/2005  Request to interconnect 172MW on the AEPW system Impact Study completed August 2006  Download 

Please send your requests to GIStudies@spp.org :

Manager, Generation Interconnections
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR 72223-4936

If you have any questions, please email GIStudies@spp.org or submit a ticket on RMS.