The following Generation Interconnection Studies have been requested.

Study NumberDate RequestedPurpose of StudyRemarksReport
 1/1/1900      
DISIS-2009-001 9/30/2009  Definitive Interconnection System Impact Study Posted 1/31/2010 - Reposted 2/5/2010  Download 
DISIS-2009-001 9/30/2009  DISIS-2009-001 Appendices Posted 1/31/2010  Download 
DISIS-2009-001 9/30/2009  DISIS-2009-001 Appendices Posted 1/31/2010 - Reposted 2/5/2010  Download 
DISIS-2009-001-1 3/1/2010  Definitive Interconnection System Impact ReStudy Posted 6/4/2010  Download 
DISIS-2009-001-2 11/1/2010  Definitive Interconnection System Impact ReStudy Posted 1/18/2011  Download 
DISIS-2009-001-3 11/1/2010  Definitive Interconnection System Impact ReStudy Posted 4/14/2011  Download 
DISIS-2009-001-4 3/1/2010  Definitive Interconnection System Impact ReStudy  Posted 1/22/2013  Download 
DISIS-2009-001-6 11/1/2010  Definitive Interconnection System Impact ReStudy Posted 11/18/2013  Download 
GEN-2009-008 7/13/2011  Limited Operation Impact Study for Generation Interconnection Request Posted 3/12/2013  Download 
GEN-2009-008 11/12/2012  Restudy to Interconnect 198.8MW to the MIDW transmission system  Posted 2/19/2013  Download 
GEN-2009-008 11/13/2012  Impact Restudy for Generator Modification (Turbine change) Posted 2/17/2015  Download 
GEN-2009-008 7/13/2011  Limited Operation Impact Study for Generation Interconnection Request  Posted 8/31/2011  Download 
GEN-2009-008 8/31/2010  Study to Interconnect 200.1MW to the MIDW transmission system  Posted 4/4/2011  Download 
GEN-2009-011 11/22/2010  Restudy to Interconnect 49MW to the MKEC transmission system Posted 2/23/2011  Download 
GEN-2009-011 11/22/2010  Limited Operation Impact Study for Generation Interconnection Request  Posted 4/21/2011  Download 
GEN-2009-016 2/10/2011  Restudy to Interconnect 100.8MW to the AEPW transmission system  Posted 5/6/2011  Download 
GEN-2009-016 3/8/2013  Generator Modification Evaluation (Turbine Change) Posted 4/9/2013  Download 
GEN-2009-017-DISIS 9/30/2009  DISIS for GEN-2009-017 Posted 3/1/2010  Download 
GEN-2009-020 9/10/2010  Limited Operation Impact Study for Generation Interconnection Request  Posted 5/5/2011  Download 
GEN-2009-020 9/10/2010  Restudy to Interconnect 49.6MW to the OKGE transmission system Posted 2/16/2011  Download 
GEN-2009-020 9/10/2010  Re-Study to Interconnect 48.3 MW to the OGE transmission system Posted 3/1/2013  Download 
GEN-2009-020 9/10/2010  Limited Operation Impact Study for Generation Interconnection Request  Posted 3/1/2013  Download 
GEN-2009-020 11/20/2012  Impact Restudy for Generator Modification (Turbine Change) Posted 2/27/2014  Download 
GEN-2009-025 3/30/2010  Restudy to Interconnect 60 MW on the OKGE transmission system  Revised Posting 10/13/2011  Download 
GEN-2009-025 3/30/2010  Restudy to Interconnect 60 MW on the OKGE transmission system Posted 6/7/2010  Download 
GEN-2009-040 8/5/2014  Impact Restudy for Generator Modification (Turbine Change)  Posted 8/27/2014  Download 
GEN-2009-040 11/6/2013  Impact Restudy for Generator Modification (Turbine Change) Posted 2/11/2014  Download 
PISIS-2009-001 9/30/2009  Preliminary Impact Study Appendix N-O Posted 3/30/2010  Download 
PISIS-2009-001 9/30/2009  Preliminary Impact Study Posted 2/26/2010 - Reposted 3/12/2010  Download 

Please send your requests to GIStudies@spp.org :

Manager, Generation Interconnections
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR 72223-4936

If you have any questions, please email GIStudies@spp.org or submit a ticket on RMS.