2013_Feasibility_Studies
The following Generation Interconnection Studies have been requested.

Study NumberDate RequestedPurpose of StudyRemarksReport
FCS-2013-003 7/11/2013  Feasibility Cluster Study Posted 8/26/2013  Download 
FCS-2013-004 11/6/2013  Feasibility cluster Study Posted 12/20/2013  Download 

Please send your requests to GIStudies@spp.org :

Manager, Generation Interconnections
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR 72223-4936

If you have any questions, please email GIStudies@spp.org or submit a ticket on RMS.