2015_Impact_Studies | |
The following Generation Interconnection Studies have been requested. |
Study Number | Date Requested | Purpose of Study | Remarks | Report |
---|---|---|---|---|
DISIS-2015-001 | 3/31/2015 | Definitive Interconnection System Impact Study DISIS-2015-001 | Posted 8/28/2015 | Download |
DISIS-2015-001-1 | 3/31/2015 | Definitive Interconnection System Impact Study DISIS-2015-001-1 | Posted 12/23/2015 | Download |
DISIS-2015-001-2 | 3/31/2015 | Definitive Interconnection System Impact Study DISIS-2015-001-2 | Posted 3/9/2016 | Download |
DISIS-2015-001-3 | 3/31/2015 | Definitive Interconnection System Impact Study DISIS-2015-001-3 | Posted 9/1/2017 | Download |
DISIS-2015-002 | 9/30/2015 | Definitive Interconnection System Impact Study DISIS-2015-002 | Posted 4/29/2016 | Download |
DISIS-2015-002-1 | 9/30/2015 | Definitive Interconnection System Impact Study DISIS-2015-002-1 | Posted 8/5/2016 | Download |
DISIS-2015-002-2 | 9/30/2015 | Definitive Interconnection System Impact Study DISIS-2015-002-2 | Posted 11/29/2016 | Download |
DISIS-2015-002-3 | 9/30/2015 | Definitive Interconnection System Impact Study DISIS-2015-002-3 | Posted 7/10/2017 | Download |
DISIS-2015-002-4 | 9/30/2015 | Definitive Interconnection System Impact Study DISIS-2015-002-4 | Posted 11/2/2017 | Download |
DISIS-2015-002-5 | 9/30/2015 | Definitive Interconnection System Impact Study DISIS-2015-002-5 | Posted 2/16/2018 | Download |
GEN-2015-001 | 9/17/2015 | Impact Restudy for Generator Modification (Turbine Change) | Posted 11/6/2015 | Download |
GEN-2015-005 | 12/6/2016 | Impact Restudy for Generator Modification (Turbine Change) | Posted 12/14/2016 | Download |
GEN-2015-013 | 5/26/2016 | Modification Request Impact Study | Posted 7/8/2016 | Download |
GEN-2015-014 | 3/13/2017 | Limited Operation Impact Study for Generation Interconnection Request | Re-Posted 10/4/2017 | Download |
GEN-2015-015 | 5/30/2017 | Impact Restudy for Generator Modification (Turbine Change) | Posted 10/10/2017 | Download |
GEN-2015-021 | 5/11/2016 | Impact Restudy for Generator Modification (Inverter Change) | Posted 8/1/2016 | Download |
GEN-2015-022 | 6/24/2016 | Modification Request Impact Study | Posted 7/20/2016 | Download |
GEN-2015-022 | 6/10/2016 | Modification Request Impact Study | Posted 6/17/2016 | Download |
GEN-2015-024 | 5/22/2016 | Impact Restudy for Generator Modification | Posted 6/22/2016 | Download |
GEN-2015-025 | 5/22/2016 | Impact Restudy for Generator Modification | Posted 6/22/2016 | Download |
GEN-2015-034 | 3/23/2016 | Impact Restudy for Generator Modification (Turbine Change) | Posted 3/30/2017 | Download |
GEN-2015-034 | 3/23/2016 | Impact Restudy for Generator Modification (Turbine Change) | Posted 4/14/2017 | Download |
GEN-2015-034 | 3/23/2016 | Impact Restudy for Generator Modification (Turbine Change) | Posted 4/28/2017 | Download |
GEN-2015-047 | 3/17/2017 | Impact Restudy for Generator Modification (Turbine Change) | Posted 5/25/2017 | Download |
GEN-2015-053 | 7/7/2017 | Impact Restudy for Generator Modification (Turbine Change) | Posted 3/21/2018 | Download |
GEN-2015-057 | 1/11/2017 | Impact Restudy for Generator Modification (Turbine Change) | Posted 4/28/2017 | Download |
GEN-2015-063 | 2/17/2017 | Impact Restudy for Generator Modification (Turbine Change) | Posted 6/23/2017 | Download |
GEN-2015-073 | 4/28/2016 | Impact Restudy for Generator Modification (Turbine Change) | Posted 3/30/2017 | Download |
GEN-2015-087 | 3/15/2017 | Limited Operation Impact Study for Generation Interconnection Request | Posted 3/16/2017 | Download |
GEN-2015-088 | 3/15/2017 | Limited Operation Impact Study for Generation Interconnection Request | Posted 3/16/2017 | Download |
GEN-2015-096 | 10/19/2015 | Limited Operation Impact Study for Generation Interconnection Request | Posted 9/14/2016 | Download |
GEN-2015-096 | 11/8/2016 | Impact Restudy for Generator Modification (Turbine Change) | Posted 11/15/2016 | Download |
GEN-2015-098 | 6/22/2016 | Impact Restudy for Generator Modification (Turbine Change) | Posted 8/24/2016 | Download |
PISIS-2015-001 | 3/31/2015 | Preliminary Interconnection System Impact Study PISIS-2015-001 | Posted 8/28/2015 | Download |
PISIS-2015-002 | 9/30/2015 | Preliminary Interconnection System Impact Study PISIS-2015-002 | Posted 4/25/2016 | Download |
Please send your requests to GIStudies@spp.org :
Manager, Generation Interconnections
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR 72223-4936
If you have any questions, please email GIStudies@spp.org or submit a ticket on RMS.