2016_Impact_Studies
The following Generation Interconnection Studies have been requested.

Study NumberDate RequestedPurpose of StudyRemarksReport
DISIS-2016-001 3/31/2016  Definitive Interconnection System Impact Study DISIS-2016-001  Posted 2/28/2017  Download 
DISIS-2016-001-1 3/31/2016  DISIS-2016-001 Restudy #1 (Revised) Posted 12/22/2017  Download 
DISIS-2016-001-2 3/31/2016  DISIS-2016-001 Restudy #2 Report Due 5/7/2018  Download 
DISIS-2016-002 11/30/2016  Definitive Interconnection System Impact Study DISIS-2016-002 Posted 4/19/2018  Download 
GEN-2016-004 5/8/2017  Impact Restudy for Generator Modification Posted 3/21/2018  Download 
GEN-2016-022 4/19/2017  Impact Restudy for Generator Modification Posted 3/21/2018  Download 
GEN-2016-036 12/20/2017  Interim Availability Impact Study for Generation Interconnection Request  Posted 3/7/2018  Download 
GEN-2016-043 3/6/2017  Impact Restudy for Generator Modification Posted 3/21/2018  Download 
GEN-2016-071 9/19/2017  Impact Restudy for Generator Modification  Posted 3/21/2018  Download 
GEN-2016-098 7/26/2017  Interim Availability Impact Study for Generation Interconnection Request  Posted 3/15/2018  Download 
PISIS-2016-001 3/31/2016  Preliminary Interconnection System Impact Study PISIS-2016-001  Posted 10/31/2016  Download 
PISIS-2016-002 11/30/2016  Preliminary Interconnection System Impact Study PISIS-2016-002 No requests were entered in this queue cluster   

Please send your requests to GIStudies@spp.org :

Manager, Generation Interconnections
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR 72223-4936

If you have any questions, please email GIStudies@spp.org or submit a ticket on RMS.