2016_Impact_Studies
The following Generation Interconnection Studies have been requested.

Study NumberDate RequestedPurpose of StudyRemarksReport
DISIS-2016-001 3/31/2016  Definitive Interconnection System Impact Study DISIS-2016-001  Posted 2/28/2017  Download 
PISIS-2016-001 3/31/2016  Preliminary Interconnection System Impact Study PISIS-2016-001  Posted 10/31/2016  Download 

Please send your requests to GIStudies@spp.org :

Manager, Generation Interconnections
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR 72223-4936

If you have any questions, please email GIStudies@spp.org or submit a ticket on RMS.