InterfaceStudy PeriodImpact Study Number Request NumberPerformedDate PostedReport
WFEC to ERCOTN  6/1/15 to 9/1/15 SPP-2015-001  80771824 February 9, 2015  February 11, 2015  Download
DOGWOOD.KELSON to SEG  6/1/15 to 10/1/15 SPP-2015-002  80850153 February 23, 2015  February 24, 2015  Download
WFEC to ERCOTN  6/1/15 to 9/1/15 SPP-2015-003  80771827 March 5, 2015  March 6, 2015  Download
DOGWOOD.MJMEUC to MOWR_MOPEPMPS  5/1/15 to 7/1/15 SPP-2015-004  80853925 March 9, 2015  March 10, 2015  Download
WFEC to ERCOTN  7/1/15 to 9/1/15 SPP-2015-007  80997860 April 23, 2015  April 24, 2015  Download
DOGWOOD.MJMEUC to MOWR_MOPEPMPS  8/1/15 to 10/1/15 SPP-2015-008  81157682 May 15, 2015  May 18, 2015  Download
WFEC to ERCOTN  9/1/15 to 9/5/15 SPP-2015-009  81571902 August 21, 2015  August 21, 2015  Download
DOGWOOD.MJMEUC - MOWR_MOPEPMPS  10/1/15 to 1/1/16 SPP-2015-010  81596418 August 31, 2015  September 1, 2015  Download
WR.FR2W.TSA to SECI_KMEA_GARC  12/30/15 to 12/1/16 SPP-2015-011  81823764 November 9, 2015  November 10, 2015  Download
GRDA_HUB to SECI_KMEA_GARC  1/1/16 to 12/1/16 SPP-2015-013  81823782 November 9, 2015  November 10, 2015  Download
DOGWOOD.MJMEUC to MOWR_MOPEPMPS  1/1/16 to 7/1/16 SPP-2015-014  81878982 November 23, 2015  November 23, 2015  Download

Please send your requests to Steve Purdy :

Steve Purdy
Manager, Transmission Service Studies
Southwest Power Pool Inc.
201 Worthen Drive
Little Rock, AR 72223-4936

If you have any questions, please call at 501-614-3371.